Skip to main content
Docs / Worked Examples
Docs Menu

Worked Examples

Build saved cases for solar, storage, and network-tariff screening. These examples use synthetic assumptions and show the model outputs returned for those inputs.

Checked on 6 November 2026. Examples A, B, and C completed in Quick Estimate. Example D completed a two-option screen in Detailed Engineering Case. All four cases were saved.

For a size sweep with a different load and cost basis, jump to Riverbend cold store: nine solar and battery designs.

Before you start

Open Project Modelling. Follow Scope, Profiles, Design, Value, Options, Run, and Results. Use Save case revision to save each case. Use Case history to reopen it. Save your current work before starting another case.

Examples A–D use the inputs below as well as their own inputs table. The demand profile is generated with Use estimated load shape. No CSV upload is needed. The profile card marks the estimate for review.

Shared inputs

InputValue
CurrencyAUD
Annual site load500000 kWh/year
Peak site demand150 kW
Existing generation0 kWh/year
Baseline load power factor0.95
Load profileUse estimated load shape; synthetic, 30-minute; Australia/Sydney; kW
Existing generation profileTransparent generic template
Network input sourceCurrent map; no electrical network or point of connection selected; no snapshot captured
Connection directionImport and export
Nominal voltage0.4 kV
Import limit300 kW
Export limit100 kW (D sweeps 0 and 100 kW)
Network screening criteriaMinimum voltage 0.95 pu; maximum voltage 1.05 pu; maximum thermal loading 100%; minimum connection headroom 0 kW; reverse power flow Allowed
Analysis horizon20 years
WACC / discount rate8%
Inflation2.5%
Energy escalation / Export escalation2% / 2%
Opex escalation2.5%
Quick self-consumption assumption70%
Export energy value0.08 AUD/kWh; example assumption, not supplied by the network tariff
FCAS / capacity revenue0 AUD/year
Grid services capacity revenue0 AUD/kW/year
Generation capacity value0 AUD/kW/year
Emissions factor / Carbon value0.65 kg CO₂-e/kWh / 0 AUD/t CO₂-e
Case decommissioning cost0 AUD
Chronological value profilesFlat import value, flat export value, flat emissions factor; none uploaded
Ranking metricNPV
No electrical network or point of connection is selected in these cases. The No network and No POC chips are intentional limits of these financial examples. Quick Estimate does not evaluate network constraints. Choosing a network tariff manually does not select an electrical network or a connection point.

A. Business solar and battery with a network tariff

This case demonstrates a library tariff and its limits. It is a network-charge-only screening case, not a complete retail bill.

Inputs

InputValue
Case nameDocs example A business solar and battery
Engineering notesSynthetic business example with annual assumptions and an estimated load shape.
ModeQuick Estimate
Network tariffAustralia → Ausgrid → EA305 · LV 160-750 MWh (system), 2026-27; selected manually
Tariff applicationApply simple averages; full rules unavailable
Import energy value0.02607 AUD/kWh; network charges only
Storage charging value0.02607 AUD/kWh
Demand value0 AUD/kW/month; library demand rate unavailable
Additional fixed annual charge9294.86 AUD/year
Control policyMaximise self-consumption
Sweep 1Primary applicable asset; Generator capacity (kW); Values 100
Solar asset name / Power factorSolar PV / 0.95
AC capacity / Inverter limit100 kW / 100 kW
Annual yield / DC / AC ratio1500 kWh/kW / 1.2
Availability profileUse annual assumption; no measured solar profile
Solar installed capex / Annual opex110000 AUD / 1500 AUD/year
Solar annual degradation0.5%
Solar replacement / DecommissioningReplacement year blank; replacement cost 0%; decommissioning cost 0 AUD
Battery asset name / Power factorBattery storage / 0.95
Battery power / Usable energy50 kW / 100 kWh
Minimum / Maximum SOC10% / 90%
Initial / Terminal SOC50% / 50%
Charge / Discharge efficiency95% / 95%
Self-discharge / Operating reserve0.1%/day / 10%
CouplingAC coupled
Battery installed capex / Annual opex90000 AUD / 1000 AUD/year
Battery annual degradation2%
Battery replacementYear 12; 50% of battery capex
Battery decommissioning cost0 AUD

Steps

  1. In Scope, name the case and enter the shared connection limits. Keep Quick Estimate selected.
  2. In Profiles, enter the shared demand values. Set Timezone to Australia/Sydney, then select Use estimated load shape.
  3. In Design, configure Solar PV. Choose Battery storage and select Add Asset. Enter the sizes and costs above.
  4. In Value, choose Australia, Ausgrid, and EA305 · LV 160-750 MWh (system).
  5. Read the tariff card. For this capture it reports demand-0: day schedule is missing or unsupported. Full rules cannot be used. Select Apply simple averages, then set Storage charging value to 0.02607. Leave the separate example export value at 0.08.
  6. In Options, set the generator-capacity sweep to 100. Save the case, open Run, and select Screen 1 variant.
  7. When the run shows completed, open Results, then Summary and Economics.
Estimated demand profile for the business example
The generated demand shape is synthetic and remains marked for review.
Solar size and cost inputs
Solar inputs: 100 kW AC, 110000 AUD capex, and 1500 AUD annual opex.
Battery operating limits and lifecycle costs
Battery inputs: 50 kW, 100 kWh, 90000 AUD capex, and a year-12 replacement.
Ausgrid EA305 tariff card and simple averages warning
EA305 is a 2026-27 time-of-use and demand network tariff. This card permits simple averages, not its full rules.
Applied network-charge averages
The applied import value is 0.02607 AUD/kWh. The separate 0.08 AUD/kWh export value is an example assumption.
Single generator capacity option
A single 100 kW generator-capacity option keeps the design size unchanged.
Completed run with review items
The run completed, but the missing network, connection point, and snapshot remain review items.

Results as shown

InputValue
NPV-A$300,007
Total capexA$200,000
First year revenue and savingsA$5,058
First year opexA$11,795
Annual generation150,000 kWh
Annual onsite use125,440 kWh
IRR / Payback— / —
Engineering gatereview
Business solar and battery summary results
Actual displayed results. The option is marked review, not Recommended.
Business solar and battery economics cards
The Economics view shows financial metric cards.

The savings are small because the import value covers network charges only. It does not include the retail energy price. The library is not a complete electricity bill, and its unavailable demand rate contributes no demand value in this case.

The opex inputs are 1500 AUD/year for solar, 1000 AUD/year for the battery, and 9294.86 AUD/year from the tariff's fixed charge. Together they are 11794.86 AUD/year; the product displays A$11,795. This exceeds the displayed first-year savings. Do not treat the negative NPV as a conclusion about the same equipment under a complete retail contract.

B. Solar PV with simple import and export values

This case uses a stated retail import assumption instead of the network-only value in A. It has no battery and no library tariff.

Inputs

InputValue
Case nameDocs example B solar only
Engineering notesSynthetic business example; simple retail import and export assumptions; no network assessment.
ModeQuick Estimate
Network tariffNone selected
Import energy value0.25 AUD/kWh; example retail import assumption
Storage charging value0.15 AUD/kWh; unused because no battery
Demand value / Additional fixed annual charge0 AUD/kW/month / 0 AUD/year
BatteryNone
Sweep 1Primary applicable asset; Generator capacity (kW); Values 100
Solar asset name / Power factorSolar PV / 0.95
AC capacity / Inverter limit100 kW / 100 kW
Annual yield / DC / AC ratio1500 kWh/kW / 1.2
Availability profileUse annual assumption; no measured solar profile
Solar installed capex / Annual opex110000 AUD / 1500 AUD/year
Solar annual degradation0.5%
Solar replacement / DecommissioningReplacement year blank; replacement cost 0%; decommissioning cost 0 AUD

Steps

  1. Create the named case in Quick Estimate. Enter the shared scope and profile inputs.
  2. Keep one Solar PV asset and enter the solar inputs above.
  3. In Value, leave the network tariff unselected. Set Import energy value to 0.25 and Export energy value to 0.08.
  4. In Options, use one generator-capacity value: 100. Save the case and select Screen 1 variant in Run.
  5. Open Results after the run completes.
Simple import and export values for solar only
Import is 0.25 AUD/kWh and export is 0.08 AUD/kWh. Both are example assumptions.
Completed solar-only run
The solar-only run completed with review items.

Results as shown

InputValue
NPVA$264,646
IRR29.42%
Discounted payback4.48 y
Total capexA$110,000
First year revenue and savingsA$29,850
First year opexA$1,500
Annual generation150,000 kWh
Annual onsite use105,000 kWh
Engineering gatereview
Solar-only summary results
These are Quick Estimate results, using a 70% self-consumption assumption.
Solar-only economics cards
The product displays NPV A$264,646 and discounted payback 4.48 years.

Do not compare A and B as a battery investment decision: their import values and fixed charges differ. Keep the same valuation basis when comparing equipment.

C. Battery-only demand-charge screening

This modelled case compares a battery using an annual demand-charge assumption.

Inputs

InputValue
Case nameDocs example C battery demand reduction
Engineering notesSynthetic business example; peak shaving objective; simple demand charge assumption; no network assessment.
ModeQuick Estimate
Network tariffNone selected
Solar PVRemoved; no generation asset
Import energy value / Storage charging value0.25 AUD/kWh / 0.25 AUD/kWh; example retail assumptions
Demand value20 AUD/kW/month; example assumption
Additional fixed annual charge0 AUD/year
Control policyPeak shaving
Sweep 1Primary applicable asset; Storage power (kW); Values 50
Battery asset name / Power factorBattery storage / 0.95
Battery power / Usable energy50 kW / 100 kWh
Minimum / Maximum SOC10% / 90%
Initial / Terminal SOC50% / 50%
Charge / Discharge efficiency95% / 95%
Self-discharge / Operating reserve0.1%/day / 10%
CouplingAC coupled
Battery installed capex / Annual opex90000 AUD / 1000 AUD/year
Battery annual degradation2%
Battery replacementYear 12; 50% of battery capex
Battery decommissioning cost0 AUD

Steps

  1. Create the named case in Quick Estimate and enter the shared inputs.
  2. In Design, remove the starting Solar PV asset. Add Battery storage, enter the battery inputs, and set Control policy to Peak shaving.
  3. In Value, set import and charging values to 0.25 and Demand value to 20. Do not select a library tariff.
  4. In Options, select Storage power (kW) and enter 50.
  5. Save the case. Select Screen 1 variant, then review Summary, Energy, and Economics.
Battery-only design with peak shaving policy
The starting solar asset was removed. Peak shaving is the selected battery policy.
Battery demand and charging value assumptions
The demand value is 20 AUD/kW/month. Charging and import both use 0.25 AUD/kWh.

Results as shown

InputValue
NPVA$31,754
IRR12.01%
Discounted payback10.83 y
Total capexA$90,000
First year revenue and savingsA$11,448
First year opexA$1,000
Annual generation0 kWh
Annual onsite use20,440 kWh
Annual import502,208.2 kWh
Annual export0 kWh
Engineering gatereview
Battery-only summary results
The quick screen reports NPV A$31,754 and discounted payback 10.83 years.
Battery-only annual energy results
Annual import exceeds the 500,000 kWh site load. Storage losses matter; a battery is not a generation source.
Battery-only economics cards
Revenue and savings are annual modelled outputs.
The selected Peak shaving policy does not turn Quick Estimate into an interval-based demand-billing study. Confirm monthly peaks, tariff demand rules, charging losses, and dispatch with suitable interval data before relying on demand savings.

D. Compare two export-limit options

This comparison keeps equipment and costs fixed and changes the export limit from 0 kW to 100 kW. It uses a stated retail import assumption, not the network-only value in A. Both options include solar and storage.

Inputs

InputValue
Case nameDocs example D export limit comparison
Engineering notesSynthetic business example; compare export limits 0 and 100 kW for identical equipment and example retail values.
ModeDetailed Engineering Case
Network tariffNone selected
Import energy value / Storage charging value0.25 AUD/kWh / 0.25 AUD/kWh; example retail assumptions
Demand value20 AUD/kW/month; example assumption
Additional fixed annual charge0 AUD/year
Control policyMaximise self-consumption
Sweep 1Primary applicable asset; Export limit (kW); Values 0, 100
Solar asset name / Power factorSolar PV / 0.95
AC capacity / Inverter limit100 kW / 100 kW
Annual yield / DC / AC ratio1500 kWh/kW / 1.2
Availability profileUse annual assumption; no measured solar profile
Solar installed capex / Annual opex110000 AUD / 1500 AUD/year
Solar annual degradation0.5%
Solar replacement / DecommissioningReplacement year blank; replacement cost 0%; decommissioning cost 0 AUD
Battery asset name / Power factorBattery storage / 0.95
Battery power / Usable energy50 kW / 100 kWh
Minimum / Maximum SOC10% / 90%
Initial / Terminal SOC50% / 50%
Charge / Discharge efficiency95% / 95%
Self-discharge / Operating reserve0.1%/day / 10%
CouplingAC coupled
Battery installed capex / Annual opex90000 AUD / 1000 AUD/year
Battery annual degradation2%
Battery replacementYear 12; 50% of battery capex
Battery decommissioning cost0 AUD

Steps

  1. Create the named case and select Detailed Engineering Case.
  2. Enter the shared inputs and the solar and battery inputs above. Keep Maximise self-consumption as the battery policy.
  3. In Value, set import and charging values to 0.25, export to 0.08, and demand value to 20. These are example retail assumptions; no library tariff is selected.
  4. In Options, choose Export limit (kW). Enter 0, 100. The equipment and its capex are the same for both options.
  5. Save the case and select Screen 2 variants.
  6. After the run shows completed, open Results and read both rows in Solution gates and ranking.
Retail value assumptions for the option comparison
Import and charging are 0.25 AUD/kWh; export is 0.08 AUD/kWh; demand value is 20 AUD/kW/month.
Export-limit sweep with two options
The design space contains export limits of 0 kW and 100 kW.
Completed two-option detailed screen
Both variants completed. Missing network evidence and the generic solar resource remain review items.

Comparison as shown

OptionGateNPVIRRPayback
connection.exportLimitKw=100reviewA$430,72227.79%4.73 y
connection.exportLimitKw=0reviewA$428,58627.7%4.75 y
Two returned export-limit options ranked by NPV
The 100 kW export limit ranks above zero export on NPV. Both options are review, not Recommended.

Leading option results as shown

The case summary and result cards show the leading 100 kW export-limit option.

InputValue
Total capexA$200,000
First year revenue and savingsA$51,370
First year opexA$2,500
Annual generation150,000 kWh
Annual onsite use146,661.02 kWh
Annual import353,338.98 kWh
Annual export2,010.51 kWh
Annual curtailment0 kWh
Chronological interval count8,760
Completed variant count / Pass count2 / 0
Economics cards for the leading comparison option
The leading option displays NPV A$430,722, IRR 27.79%, and discounted payback 4.73 years.
Annual energy results for the leading comparison option
The detailed run shows 146,661.02 kWh annual onsite use and 2,010.51 kWh exports.
These are economic and dispatch results from synthetic demand and a generic solar shape. No electrical network or point of connection is selected. The Network view states that required engineering checks or supporting evidence remain unassessed.

E. Riverbend cold store: compare nine solar and battery designs

Riverbend cold store is a fictional refrigeration site. Its cold rooms draw power overnight. Daytime handling and daily defrost cycles add to demand. Would a bigger rooftop array or a longer-duration battery repay its extra cost? This example holds the load and prices fixed and compares nine designs against buying all electricity from the grid.

Watch this example in 47 seconds, with sound: the nine designs ranked by NPV, then network context and engineering status. The network scenes show an illustrative case, not Riverbend.

Set up the comparison

  1. Use Detailed Engineering Case in Project Modelling. Give every option the same synthetic hourly load and solar profiles. The load is 595 MWh for the year, with a peak of 99.8 kW.
  2. In Design, pair one solar array with one AC-coupled battery. Keep battery power at 60 kW. Use size-based costs so the capital cost changes with the equipment size.
  3. In Options, sweep the solar generator’s modelled AC capacity over 120, 200, 280 kW and storage energy over 60, 120, 180 kWh. Each solar size is paired with each battery size, giving nine designs.
  4. Screen the nine variants, then open Results → Summary → Design value by solar size. Select a column to identify its equipment and read its NPV. Use the gates table to check what the screen assessed.

The results below come from these synthetic profiles. Substituting your site’s profiles or costs can change the order.

Inputs used for these results
  • Profiles: 8,760 synthetic hourly values in 2025. The PV shape yields 1,453 kWh per kW of nameplate in the model year before curtailment. No customer meter or real site data was used.
  • Operating limits: 150 kW import, 70 kW export. The battery serves onsite load, with 95% charge efficiency, 95% discharge efficiency and a 10–90% state-of-charge range.
  • Value: 15 years at a 7% discount rate. Grid imports cost AUD 0.23/kWh and exports earn AUD 0.045/kWh. No inflation or price escalation; no revenue for demand reduction or backup operation.
  • Equipment costs: solar AUD 1,150/kW; storage AUD 260/kW of power plus AUD 600/kWh of capacity. Annual operating costs are 1% of solar capex and 1.5% of storage capex. PV output degrades by 0.5% per year. The year 11 battery replacement allowance is 45% of battery capex.

Read the nine columns

The leftmost column has the highest net present value (NPV) among the designs tested. Colour identifies the solar PV nameplate (AC capacity in kW); it does not show battery size. Look for the same PV colour at different ranks to see how changing battery energy affected the result.

The first of nine columns is selected: 200 kW of solar and 60 kWh of storage. Columns to its right have lower NPVs. The table below lists all nine values.
The 200 kW array with the 60 kWh battery ranks first at A$209,861. Each column is one design, not one year.
Nine designs by NPV (nearest AUD)
RankSolar PV (kW)Battery (kWh)NPV (AUD)
120060209,861
228060192,634
3200120178,789
4280120171,372
5280180150,316
6200180143,668
712060134,283
812012085,680
912018037,065

What changes at 280 kW?

Keep the 60 kW / 60 kWh battery and select the second column. The extra 80 kW of solar takes the upfront cost from A$281,600 to A$373,600. In the first year, exports rise from 35.1 to 102.8 MWh, while energy curtailed at the 70 kW export limit rises from 0.1 to 20.8 MWh. With exports worth 4.5¢/kWh against 23¢/kWh for avoided imports, the extra savings and export income do not cover the larger array’s additional costs over 15 years at the 7% discount rate.

The second column is selected. Its detail shows the 280 kW solar design with 60 kWh of storage; the higher-value 200 kW design remains to the left.
The 280 kW design ranks second at A$192,634, about A$17,200 below the 200 kW design with the same battery.

Limit: all nine designs have an engineering status of review. This is a chronological dispatch and financial screen with assumed limits, not an AC network study. No electrical network or connection rating was verified. The leading column is neither a connection approval nor a claim that this size is optimal. PV-only designs and other sizes were not tested.

How to read the design value chart · How NPV differs from annual cash flow.

Cash flow and reports

The versioned Economics tab shows metric cards and a separate Cashflow explorer. See Value and Finance for an annual table, CSV and reconciliation example. The Report view offers evidence and report controls.

Legacy Estimates has separate Cumulative Cash Flow and Annual Cash Flow charts. They belong to the legacy calculator, not the cases above. See the legacy guide before using that separate calculation path.

More tested examples

The following guides include more worked examples with explicit model assumptions:

Related Guides

Can't find what you need? Email support@networkmap.energy or call 1300 936 116. Sign in to Network Map.