Skip to main content
Docs / DER Design
Docs Menu

DER Design

Configure solar, wind, hydro, biomass, storage, and load changes at the case's point of connection.

Add and manage assets

  1. Open DER Design.
  2. Choose Asset type.
  3. Select Add Asset.
  4. Enter Asset name under Identity & connection.
  5. Complete Sizing & operation.
  6. Complete Costs & lifecycle.

A new case already contains one Solar PV asset. You can add several assets, including several of the same type. The asset count appears above the cards. Use the delete button on an asset card to remove that asset. Keep at least one DER or load-adjustment asset to run the case.

All cards use the point of connection selected in Map Scope & Connection. There is no separate connection-point selector on each card. Each card shows its type, connection-point name, and source.

Replace the starting assumptions with specifications for the proposed equipment. Set the network connection limit separately from the equipment size.

Common identity and connection fields

FieldDefaultUse
Asset nameThe asset type name.Use a unique, useful name. It appears in asset selectors and sweep targets.
Power factor0.95Shown for generation and storage, but not load adjustment. Generator power factor informs reactive-power modelling. Do not treat this field alone as a verified inverter-control model.

Solar PV

FieldDefaultMeaning
AC capacity500 kWInstalled AC generation capacity.
Annual yield1,500 kWh/kWAnnual energy assumption per kW of capacity.
DC / AC ratio1.2Ratio of DC array capacity to AC capacity.
Inverter limit500 kWAC inverter output limit.
Availability profileUse annual assumptionChoose an attached resource-availability or generation profile for the chronological shape. Supply normalized pu values from 0 to 1.

Detailed solar dispatch uses the availability shape and DC/AC sizing, with AC capacity and inverter limits. A positive Annual yield scales the shape toward the annual energy target, subject to output limits. A generic solar shape needs review. Attach a suitable interval resource profile for a detailed conclusion.

Solar input example

Solar capacity, yield, and lifecycle inputs
The example uses 100 kW AC, an annual yield of 1500 kWh/kW, and 110000 AUD installed capex.

Wind

FieldDefaultMeaning
Rated capacity500 kWInstalled generator capacity.
Annual yield2,200 kWh/kWAnnual energy assumption per kW.
Derating5%Reduction applied to generation output.
Availability profileUse annual assumptionChoose an attached normalized availability or generation shape. A positive Annual yield scales the shape toward the annual energy target before derating, subject to capacity limits. The card does not calculate wind resource from site coordinates.

Hydro

FieldDefaultMeaning
Generator capacity500 kWInstalled generator capacity.
Operating modeRun of riverChoose Run of river or Dispatchable. Run-of-river output follows resource availability. Dispatchable hydro can respond within its operating assumptions.
Annual energy budget2,000,000 kWhEnergy budget for the hydro asset.
Minimum output0%Minimum operating output as a percentage of capacity.
Availability profileUse annual assumptionSelect an attached availability or generation shape. Confirm that it represents the available hydro resource.

Biomass

FieldDefaultMeaning
Generator capacity500 kWInstalled generator capacity.
Fuel / marginal cost55 per MWhVariable generation cost in the case currency per MWh.
Minimum output25%Minimum operating output as a percentage of capacity.
Ramp rate10%/minRequested change in output per minute. Confirm the operating assumption against equipment data.
Availability90%Availability multiplier.
Availability profileUse annual assumptionSelect an attached availability or generation shape when available.

Biomass is dispatchable in the detailed model. The availability, minimum-output, fuel-cost, and ramp assumptions affect its operating model. This is not a plant control-system simulation.

Battery storage

FieldDefaultMeaning
Power100 kWCharge and discharge power rating.
Usable energy200 kWhEnergy capacity entered for the model. The state-of-charge window and reserve further constrain operation.
Minimum SOC10%Lower state-of-charge boundary.
Maximum SOC90%Upper state-of-charge boundary.
Initial SOC50%State of charge at the start of the dispatch period.
Terminal SOC50%State-of-charge target at the end of the period. Review terminal-state diagnostics in detailed results.
Charge efficiency95%Efficiency when energy enters storage.
Discharge efficiency95%Efficiency when stored energy is delivered.
Self-discharge0.1%/dayDaily stored-energy loss assumption.
Operating reserve10%Capacity reserved from ordinary dispatch.
Control policyMaximise self-consumptionSelect the dispatch objective described below.
CouplingAC coupledChoose AC coupled or DC coupled. DC coupling requires follow-on review of inverter clipping and DC-bus losses.

Storage control policies

PolicyUse
Maximise self-consumptionStore excess generation and discharge against site demand.
Peak shavingUse storage to reduce peaks in site import.
Tariff arbitrageUse price differences to guide charging and discharging. Confirm the price assumptions in Value & Finance.
Network supportDispatch storage against the modelled network-support target and limits.

Storage validation

  • Power and Usable energy must be greater than zero.
  • Maximum SOC must exceed Minimum SOC.
  • Initial SOC and a supplied Terminal SOC must be inside the SOC window.
  • Operating reserve must not exceed the difference between maximum and minimum SOC.
  • Charge and discharge efficiencies must be greater than zero and no greater than 100%.

If the server reports initialSocPercent must be inside the SOC operating window, correct Initial SOC or the SOC limits. Apply the same rule to a terminal-SOC message. For reservePercent exceeds the usable SOC window, reduce the reserve or revise the SOC limits.

Battery input example

Battery power, energy, operating limits, and costs
The example uses a 50 kW / 100 kWh battery. Costs and lifecycle inputs are separate from its operating limits.

Load adjustment

FieldDefaultMeaning
Adjustment typeNew demandChoose New demand, Load growth, or Demand reduction. Demand reduction subtracts energy from baseline load; the other choices add demand.
Peak demand change250 kWPeak demand-change assumption.
Annual energy change500,000 kWhAnnual energy added or removed. Enter its magnitude; the adjustment type determines the direction.
Annual growth0%Annual growth assumption for the adjustment.
Availability profileUse annual assumptionChoose an attached availability or generation profile to shape the adjustment over time.

Provide a positive peak demand change or annual energy change. Prefer a confirmed annual energy change instead of relying on a peak-only estimate. Use the load adjustment to model the demand change, and enter the applicable connection limits separately.

Costs & lifecycle

Every asset card includes these fields. Values are asset-specific, not a single shared project budget.

FieldDefaultMeaning
Installed capex0 in the case currencyInitial installed capital cost.
Annual opex0 in the case currency per yearAnnual fixed operating cost.
Annual degradation2% for storage; 0.5% for other new asset cardsAnnual degradation assumption. Confirm its relevance to the asset type and calculation mode.
Replacement yearBlankYear when a replacement cost is incurred. Leave it blank when no replacement is specified.
Replacement cost0% of capexReplacement cost as a percentage of initial capex.
Decommissioning cost0 in the case currencyEnd-of-life cost assumption.

Enter explicit values for known costs. A blank numeric input is not evidence that a cost is zero. See Value and Finance for financial methods and lifecycle treatment.

Link profiles and options

  1. Upload the relevant files in Demand & Resource Profiles.
  2. Return to each asset card.
  3. Select its Availability profile where that control is present.
  4. Open Options to sweep generator capacity, storage power, storage energy, or storage reserve.
  5. Check that each sweep targets a compatible asset.

The availability selector offers attached Resource availability and Existing generation profiles. Choose data that matches the intended asset. Storage has its own operating controls rather than an availability selector in this workbench.

Screening and explicit performance bindings

Asset performance and charging provides typed screening attachments. An unbound screening check does not change case totals. An explicit battery capacity binding can affect saved runs. Operating-window library items can also create a load profile for a Load adjustment asset.

See Asset Screening for real input and result examples. For timed operating bounds on battery equipment, see Dispatch Calendars and Sizing.

See Shared Library for target selection, saved version pins, profile coverage and the save-and-rerun steps.

Related Guides

Can't find what you need? Email support@networkmap.energy or call 1300 936 116. Sign in to Network Map.