A contract can improve revenue while the project as a whole still needs a different investment horizon or cost structure. To see the distinction, follow the cash-flow ledger from the contract adjustment to the operating result and then back to the initial investment.

Our example is a saved Network Map Detailed case reviewed on 7 November 2026. It uses a supplied one-year hourly 2026 energy profile, an export PPA and authored costs in AUD. The results are modelled, with each layer retained in the saved evidence.

Begin With The Commercial Adjustment

The case exports 2.19 MWh under a fixed-price agreement at AUD 100/MWh. The contract replaces an existing AUD 0.04/kWh export credit. Its full settlement export shows AUD 219.00 of fixed payment, −AUD 87.60 of removed credit and an AUD 131.40 net adjustment.

That adjustment enters a project that already has energy savings and receipts. It is not the whole project revenue, and the full contract payment should not be added again. The accounting boundary is the same one used in our Contract Settlement guide.

The physical inputs are a constant 1 kW load and 2 kW solar, with a supplied daily solar profile. The saved result retains its provided-profile basis and estimate flags.

Build The Operating Cash Flow

After settlement, year-one revenue and savings are AUD 766.50. First-year operating cost is AUD 20.00. Subtracting that cost gives AUD 746.50 of year-one net cash flow.

From Revenue To Operating Net. Modelled saved case · model year 1. Revenue and savings: 766.5 AUD; Operating cost: -20 AUD; Net cash flow: 746.5 AUD.
Modelled saved case · model year 1. Revenue already includes the AUD 131.40 commercial adjustment. Source: Network Map.

Explore Project Modelling

This operating net is a useful intermediate result. It tells us what the authored year contributes after its operating cost. It does not yet account for the AUD 1,000 initial capital investment in model year zero.

Keeping the operating line separate from capital also makes a commercial comparison clearer. A change in contract terms can be traced through revenue and operating net before assessing its effect on the investment result.

Bring Back Capital And Time

The saved one-year horizon includes −AUD 1,000 at the start and AUD 746.50 in year one. Lifetime undiscounted net cash flow is therefore −AUD 253.50. At the authored 8% discount rate, lifetime discounted cash flow is −AUD 308.80.

Include Capital And The Time Value. Modelled one-year horizon · 8% discount rate. Initial investment: -1,000 AUD; Year-one net: 746.5 AUD; Lifetime net: -253.5 AUD; Lifetime discounted: -308.8 AUD.
Modelled one-year horizon · 8% discount rate. Initial investment is in year 0. Columns show related ledger measures, not additive items. Source: Network Map.

The discounted result follows from valuing the year-one cash flow at the initial date and then subtracting capital. In this example, AUD 746.50 divided by 1.08 is AUD 691.20 when rounded; after the AUD 1,000 investment, the result is −AUD 308.80.

The negative investment result and the positive contract adjustment are consistent. They describe different parts of the same case. The contract improves the annual ledger, while the chosen one-year horizon does not recover the initial investment under these assumptions.

Ask The Next Investment Question Explicitly

A project review can now test a longer supported study horizon, different equipment costs or another commercial structure. Each alternative should carry its own dated energy and financial assumptions. That preserves the original result rather than changing its meaning after the fact.

  • Read the contract adjustment inside total project revenue.
  • Separate operating net from the initial investment.
  • Use the saved horizon and discount rate when interpreting returns.
  • Compare alternatives on a consistent cash-flow basis.

Open Value And Finance for the cash-flow explorer and Comparison And Reports to retain the comparison evidence. Use Revenue Reconciliation for the wider signed-ledger workflow.