Market analysis of 7 November 2026
A connection limit can be constant, or it can change with an agreed operating window. For a project study, that distinction belongs in the time axis. A time-based capacity profile shows the import and export limits for each operating window.
Our worked configuration uses a Network Map dispatch calendar reviewed on 7 November 2026. Use the separate October 2026 curtailment dataset for market context alongside the modelled site limits.
Put The Limit On A Clock
The authored import calendar has a default ceiling of 1,000 kW. From 10:00 to 12:00 in the case timezone, UTC, the ceiling is 800 kW. The window applies across all 12 months and all 7 weekdays. These operating limits are inputs to the example study.

The tighter window removes 200 kW of import headroom relative to the default, a derived 20% reduction. Whether that change affects the project depends on the coincident load, generation and storage operation. The calendar must therefore sit on the same timestamps as the electrical profiles.
The scalar connection limit remains a hard limit. Use the calendar to express time-varying operating bounds within the physical connection envelope.
Separate Import And Export Questions
A separate reusable calendar in the documentation sets a 500 kW export ceiling with no time windows. Import and export limits describe different directions of power flow. Keep them as separate inputs when a site has both generation and demand.
For an import-constrained window, the study asks how load, storage and generation fit within the available supply. For an export-constrained window, it asks how much generation can serve the site, enter storage or reach the grid. The energy consequences follow from the coincident profiles, not from the limit alone.
Pin a reusable calendar version when the assumption is shared across cases. Saving the copied values with the case revision makes a comparison repeatable even if the library later changes.
Connect Curtailment Context To The Site Study
Network Map’s October 2026 dataset estimates 950,687 MWh of curtailed renewable energy from 5,509,954 MWh available, both rounded to whole MWh. The monthly categories are 417,271 MWh associated with network causes, 494,978 MWh with economic causes and 38,439 MWh with other causes, independently rounded.

Those categories help frame different study questions. A physical export ceiling changes what the site can send through its connection. An economic decision changes whether export is attractive at the supplied price. Both can reduce delivered energy, but they enter the project through different assumptions.
The aggregate market figures provide context for that distinction. The site’s own chronological inputs determine the effect of its particular operating window. Keeping the two evidence levels separate makes the resulting investment case easier to review.
Retain The Connection Assumption With The Run
- State the direction, unit, timezone and default limit.
- Record each operating window and its source.
- Align the calendar with demand, generation and storage intervals.
- Inspect energy results under the same limits used in the financial comparison.
Use Dispatch Calendars And Sizing for calendar bounds. Explore Grid Constraints for network context and Curtailment By Cause for the market categories. The Project Modelling guide connects these inputs to a saved case.