Skip to main content

Market analysis of 19 October 2026

The high-impact network outage schedule published on 19 October 2026 listed 3 non-withdrawn entries active on 19 October 2026.

By region, the active entries were: New South Wales 1, Victoria 1, Tasmania 1. Counts cover each entry whose scheduled window overlapped the calendar day in fixed UTC+10.

The Outage Load Around The Date

The first chart counts scheduled entries active on each day from 12 October to 26 October 2026, using the same publication. It shows whether 19 October sat inside a busy or a quiet stretch of planned network work.

Scheduled Outages Active Each Day — 19 October 2026; 12 Oct – 26 Oct 2026 | Non-Withdrawn Entries
Scheduled outage entries active per day around 2026-10-19. Source: Network Map.

The Longest Scheduled Windows

The longest active windows on the day were: Canberra ? Capital (6) 330kV Line (New South Wales), scheduled from 30 September 2026 07:19 to 19 October 2026 16:00; George Town – George Town Converter Station 220 kV Line (Tasmania), scheduled from 19 October 2026 05:30 to 23 October 2026 20:00; South Morang – Sydenham No.2 500 kV Line (Victoria), scheduled from 18 October 2026 05:31 to 21 October 2026 16:30.

The second chart shows the active entries by region.

Active Outages By Region On 19 October — 19 October 2026; 2026-10-19 | Non-Withdrawn Schedule Entries
Active scheduled outage entries by region on 2026-10-19. Source: Network Map.

Why Outage Schedules Matter

Scheduled outages reduce network capability while the work is under way. Interregional entries can lower transfer limits between regions, which links them directly to price separation and to the constraints that bind generators. Reading the schedule by date shows which days carry that exposure.

Figures use the outage schedule snapshot published on 19 October 2026, with withdrawn entries excluded and times in fixed UTC+10.

Explore The Data

Network Outages Risk, Constraint Headroom, Markets.

Sign Up To Explore Market Insights