Curtailment and grid constraint analysis, October 2026
A wind or solar farm earns only on the energy it is allowed to export. When prices fall below zero or the network around it is full, output is curtailed and the revenue is lost. Network Map tracks curtailment for every semi-scheduled wind and solar unit, split by cause, every five minutes, alongside every binding grid constraint and every planned network outage.
These eight charts, plus a bonus chart on outages, use October 2026, the most recent full month. They show how much energy was curtailed and why, which regions and hours carry the most, which grid constraints bind for longest and how to use all of this to screen a site before you commit to it.
Chart 1: Up To 83 GWh Of Wind And Solar Was Curtailed In A Day
In October 2026 semi-scheduled wind and solar units could have produced 5,510 GWh. Of that, 951 GWh was curtailed, or 17.3% of available energy. That is an average of 30.7 GWh a day.
The daily total ranged from 4.1 GWh on 5 October to 82.9 GWh on 11 October, when 36% of available energy was curtailed. On the median day 15% of available output was curtailed. On the quietest day it was 4%. The five highest days were 8 to 11 October and 19 October. On those spring days available wind and solar output was high and demand was moderate, so the grid had more energy than it could use or move.

Chart 2: Two Thirds Of Curtailment Followed Price, One Third Network Limits
Network Map splits each curtailed megawatt-hour by its cause. Economic curtailment happens when a generator reduces output because the price has fallen below its offer, usually below zero. Network curtailment happens when a grid constraint limits what the unit can export, whatever the price.
In October, 495 GWh (52%) was economic and 417 GWh (44%) was caused by network limits. The remaining 38 GWh (4%) had other causes. The difference matters for a new project. Economic curtailment can be reduced with storage, a contract or flexible demand on site. Network curtailment is set by the grid, so the location decides it.

Chart 3: Victoria Curtails Most, New South Wales Is Network-Driven
Network Map holds the full regional split for 9, 10, 11 and 19 October, four of the five highest-curtailment days of the month. On those days Victoria curtailed 45% of its available wind and solar energy, 158 GWh in total, and 83% of that was economic. South Australia curtailed 31%, almost all of it economic.
New South Wales looks very different. It curtailed 19% of available energy, and 99% of that was caused by network limits. Queensland curtailed 11%, with 57% from network limits. Tasmania curtailed 7%. The peak curtailment in a single five-minute interval was 5,709 MW in Victoria, 2,271 MW in South Australia and 2,208 MW in New South Wales.
For a developer this is the most useful split in the article. In Victoria and South Australia the main risk is price, which a battery or a contract can manage. In New South Wales and parts of Queensland the main risk is the network, which needs a careful choice of connection point.

Chart 4: On The Peak Day, Price-Driven Curtailment Ran From 7am To 6pm
Chart 4 shows 11 October hour by hour. Economic curtailment started after 6am, rose above 7,000 MW between 10am and 2pm and faded by 7pm as the sun set and prices recovered. Across the day it added up to 63.2 GWh.
Network curtailment followed a flatter shape, with 16.8 GWh across the day. It ran at 1,000 to 2,000 MW from 8am to 4pm and continued at a lower level into the evening, when wind output on constrained lines was still high. A wind farm behind a busy line can be curtailed at night as well as in the middle of the day.

Chart 5: 67% Of Curtailment Falls Between 9am And 4pm
Across the four days with five-minute totals, 67% of curtailed energy fell between 9am and 4pm. Curtailment peaked in the 12:00 hour at an average of 7.0 GW, while available wind and solar output averaged 14.6 GW in the same hour. Between 6pm and 7am only 14% of curtailed energy was lost.
This has direct consequences for project design. A solar farm sits right in the curtailment window. A wind farm produces more of its energy outside it. A battery sized to absorb four to six hours of midday output can turn the largest block of curtailed energy into evening sales.

Check Curtailment Near Your Site
Chart 6: Grid Constraints Bound For 175 Constraint-Hours A Day
A grid constraint binds when the dispatch engine has to hold back generation, or change flows, to keep a line, transformer or connection within its limit. Chart 6 counts transmission and connection constraints only, leaving out frequency and unit-specific limits.
In October these grid constraints bound for 5,413 constraint-hours in total, an average of 175 a day. On a median day 63 different grid constraints were binding at some point. The busiest day was 28 October, with 109 different constraints binding. Even the quietest day had 51. Constraints are a permanent part of how the grid runs, not an occasional event.

Chart 7: The Most-Binding Grid Constraints Held For Up To 24 Hours
Chart 7 ranks the longest-binding grid constraints across five October days by hours binding. 2 constraints were binding for the full 24 hours of a day, and 9 of the 44 constraints in the daily top tens bound for 12 hours or more. The longest belonged to limits on flows between regions and to thermal limits on lines in Queensland, which were binding for 23.6 and 23.2 hours on single days.
By type, thermal line and transformer limits accounted for 152 binding hours in the daily top tens. Limits at individual wind and solar farm connections accounted for 111. Stability and voltage limits accounted for 83. By region, constraints in New South Wales held for 158 hours, Victoria 119 and Queensland 94. One constraint appeared in the top ten on four of the five days, for 61 hours in total. A recurring constraint like this is the best early warning a developer can get.

Chart 8: Farm Limits Bind In Daylight, Line Limits Around The Clock
Chart 8 breaks the most-binding grid constraints down by hour of day. Limits at wind and solar farm connections bound almost only between 5am and 5pm, the hours when solar farms are exporting. Thermal limits on lines and flows between regions bound at every hour of the day, with only a small dip in the evening.
The hour of a constraint tells you which technology it hurts. A daylight constraint mostly costs solar. A 24-hour constraint also costs wind, and it can stop a battery from exporting at the evening peak. When you screen a site, check when the nearby constraints bind as well as how often.

Bonus Chart: Planned Network Outage Schedules Peaked In Winter
Planned outages are a common cause of new constraints. When a line is out for maintenance, the remaining network carries more load and limits bind more often. Network Map holds every published planned outage schedule from November 2025. The schedule published on 3 November 2025 listed 124 entries. By 20 July 2026 it listed 196, and the latest, 19 October 2026, lists 159.
South Australia accounts for the largest share, 38% of entries in the latest schedule, followed by Victoria and New South Wales. About 36% of entries can affect flows between regions. Check the schedule for the lines near your site before you rely on any constraint history.

A Worked Example: What Curtailment Costs A Project
The regional rates in Chart 3 can be turned into a quick estimate of lost output. This is an estimate, using the average rate on the four high-curtailment days for every unit in the region:
Lost energy = available energy x regional curtailed share.
A project with 1,000 MWh of available output on a day like these would lose about 449 MWh in Victoria, 309 MWh in South Australia, 186 MWh in New South Wales and 111 MWh in Queensland. The cause then sets the value of that loss. Economic curtailment mostly removes output that would have sold below zero, so the revenue lost is small and a battery can recover much of it. Network curtailment can remove output at any price, so its cost is closer to the full regional price for those hours. Two sites with the same curtailed share can therefore have very different revenue at risk.
How To Screen A Site
The charts above add up to a simple screening process for a new wind, solar or battery project:
- Start with the region. Check the curtailed share and its cause (Chart 3). An economic split points to storage or contracts. A network split points to the connection point.
- Check the hours. Compare your expected output profile with the curtailment hours (Charts 4 and 5). Solar overlaps most. Wind and storage overlap less.
- Look up nearby constraints. Find the grid constraints that include lines near your connection point and count their binding hours (Charts 6 and 7). A constraint that binds most days is a strong warning.
- Check when they bind. Daylight constraints cost solar. Constraints that bind around the clock also cost wind and storage (Chart 8).
- Read the outage schedule. Planned outages near the site can add constraints for weeks at a time (Bonus Chart).
- Price the curtailment. Value the curtailed hours at the regional price for those hours. Midday curtailment at negative prices costs less than evening curtailment at peak prices.
What It All Means
- Curtailment is large and measurable. 951 GWh of wind and solar energy, 17% of what was available, was curtailed in October alone.
- The cause shapes the fix. Economic curtailment (52%) responds to storage and contracts. Network curtailment (44%) responds to location.
- Regions differ in kind. Victoria and South Australia curtail mostly on price. New South Wales curtails almost entirely on network limits.
- Midday carries the risk. 67% of curtailment falls between 9am and 4pm, which favours wind and storage over stand-alone solar.
- Recurring constraints are the warning sign. The longest-binding grid constraints held for up to 24 hours a day, and some recur day after day.
Model It In Network Map
Network Map shows curtailment by cause, binding grid constraints and planned outages on the map, around the connection point you choose. Screen a site in minutes, then model a wind, solar or battery project with the curtailment that site actually sees.
Every figure comes from Network Map market data: five-minute available and dispatched energy for semi-scheduled wind and solar units, binding grid constraints in dispatch and published planned network outage schedules.