Market analysis of 21 September 2026
The high-impact network outage schedule published on 21 September 2026 listed 4 non-withdrawn entries active on 21 September 2026, 1 of them flagged as interregional.
By region, the active entries were: Victoria 2, New South Wales 1, South Australia 1. Counts cover each entry whose scheduled window overlapped the calendar day in fixed UTC+10.
The Outage Load Around The Date
The first chart counts scheduled entries active on each day from 14 September to 28 September 2026, using the same publication. It shows whether 21 September sat inside a busy or a quiet stretch of planned network work.

The Longest Scheduled Windows
The longest active windows on the day were: Upper Tumut – Stockdill (1) 330kV Line (New South Wales), scheduled from 15 September 2026 08:01 to 27 September 2026 16:00; South Morang – Sydenham No.2 500 kV Line (Victoria), scheduled from 20 September 2026 06:30 to 23 September 2026 18:00; Red Cliffs No.2 220 kV Bus (Victoria), scheduled from 21 September 2026 06:30 to 21 September 2026 19:00.
The second chart shows the active entries by region.

Why Outage Schedules Matter
Scheduled outages reduce network capability while the work is under way. Interregional entries can lower transfer limits between regions, which links them directly to price separation and to the constraints that bind generators. Reading the schedule by date shows which days carry that exposure.
Figures use the outage schedule snapshot published on 21 September 2026, with withdrawn entries excluded and times in fixed UTC+10.