Network analysis, 19 to 26 November 2026
By 9:45 pm on Thursday 19 November 2026, about 10,000 Eyre Peninsula customers had electricity again. Six days later, crews were still working on the high-voltage line that normally supplies Port Lincoln. Local generators had brought the lights back for much of Port Lincoln without reconnecting it to the wider grid.
Thursday night: a different source of electricity
ElectraNet put the time of the storm damage at about 3 pm. The transmission operator estimated that about 24,000 customers initially lost power. Its inspectors found three damaged towers between Cleve and Port Lincoln. The state emergency declaration described two towers as destroyed on the 132 kilovolt line from Cultana to Port Lincoln. The declaration took effect at 6:15 pm.
The Australian Energy Market Operator’s event notice recorded the loss of both circuits. It put the demand disconnected at about 30 megawatts, a measure of power rather than a count of premises. The market operator (AEMO) said it had not ordered power cuts. The customers supplied locally that evening were mostly in and around Port Lincoln.
Friday: the north and west regain a grid connection
By 1 pm on Friday 20 November, ElectraNet said it had changed the connections on its network to restore transmission service to the northern and western peninsula. SA Power Networks, which delivers power from that network to individual premises, was still restoring local supply. A storm can damage both levels of the network; a transmission line returning to service does not establish when any one home got power.
Mt Millar Wind Farm’s position changed that afternoon too. In AEMO’s five-minute dispatch records for Friday, the rule that capped Mt Millar at zero was still present in the interval ending at 1:30 pm. It was gone in the interval ending at 1:35 pm. Mt Millar was no longer held off by that rule. The change does not tell us how much electricity its turbines actually produced.
At 6 pm that day, SA Power Networks reported that lower Eyre Peninsula customers who had paused rooftop solar production had helped temporary generators maintain supply around Port Lincoln. The solar request applied to an area still relying on local power, not to the whole peninsula.
What Wednesday’s date meant
An AEMO network schedule published on Friday listed 5:30 pm on Wednesday 25 November as the expected end of one of the line outages. The field for its actual end was blank. By Thursday morning’s schedule, a replacement record for that outage showed it had ended on Sunday 22 November. A separate Yadnarie to Port Lincoln outage still had no recorded end. These entries describe individual lines, not a return to normal supply for homes.
At 11:30 am on Wednesday 25 November, ElectraNet said its crews were installing temporary towers. The Department for Energy and Mining had reported at 6 pm the previous day that lower peninsula customers had been advised of a planned interruption within a window from 10:30 pm Thursday 26 November to 6 am Friday 27 November. The purpose was to move the area off temporary generation. The window was not a prediction that customers would lose supply for that entire period.
At 8:14 am ACDT on Thursday 26 November, none of the three public updates from ElectraNet, SA Power Networks and the state government confirmed that Port Lincoln was back on its normal transmission supply. Even after that step, permanent towers would still be needed; ElectraNet expected those repairs to take months. Network Map’s outage guide shows how to trace a published outage schedule to the line it covers.
Topic leads: WattClarity’s reporting on the initial outage, outage estimate, rooftop solar and Mt Millar. All times above are ACDT.